ebook: Engineering Analysis using Scilab and C
   



TOC PREV NEXT

2.5 Problems


1. A new building is being constructed and the following tasks are required. The normal workdays are 7am-3pm, Monday to Friday. Overtime is possible, however the costs make it highly underiable. Write a Gantt chart for completion of the job in 3 months.

Site Preparation - 1 month
Foundations - 1 month - after Site Preparation
Framing - 2 weeks - after Foundations
Plumbing - 5 weeks - after Framing
Electrical - 6 weeks - after Framing
Inspection - after Plumbing and Electrical
Drywall - 2 weeks - after Inspection
Painting - 1 week - after Drywall
Hardware - 1 week - after Painting
Carpet - 3 days - after Painting

2. Develop a project activity network for problem 1.

3. Identiy the critical path for problem 2.

4. Consider the PERT network diagram below and find the likelyhood that the project will be complete in 40 days.

5. For problem 4, find a target completion date for the project that will make it 50% likely that it will be complete.

TOC PREV NEXT

Search for More:

Custom Search