10. PROCESS CAPABILITY
After control charts (X and R) have been developed, and the process is in control, the process capability is 6s
The capability index can be calculated for a design
The capacity Ratio can also be calculated
The Capability Index is another useful measure
Some general notes about these indices
If Cp or Cpk are both too large (>>2) the process may be too good, suggesting less expensive, easier processes could be considered.
A good rule of thumb for using Cp and Cpk is that if new equipment is being purchased, try to get values above 1.5, if the equipment is already available, 1.33 is acceptable.